Generation Mining Limited (TSX: GENM) (OTCQB: GENMF) (“Gen Mining” or the “Company”) is pleased to report strong progress at its Marathon Copper-Palladium Project in Northwestern Ontario (the “Project”). Orders are now in place for all of the Project’s major long-lead equipment, work is well under way at site, and the Project remains on track.

Highlights

  • All long-lead equipment ordered: Letters of award or purchase orders are in place for every long-lead equipment package and major contract. Procurement commitments now exceed C$500 million and are at or below the costs estimated in the most recent feasibility study and construction budget.
  • Smarter mill design: A larger SAG mill gives Marathon its full planned processing capacity of 10.1 million tonnes per year from start-up, removes the need for a pebble crusher and avoids approximately C$12 million in future expansion costs.
  • Engineering advancing: Detailed engineering by Ausenco is approximately 32% complete.
  • On track: Forecast cost at completion remains within the construction budget. Savings on equipment purchases have offset expected higher fuel costs, meaning the contingency portion of the construction budget remains intact.

Partnering with Metso

Gen Mining is working closely with equipment supplier Metso Canada Inc. (“Metso”) on Marathon’s processing plant. The work covers the primary crusher and the SAG and ball mills, and discussions are progressing on flotation equipment and pumps.

One early result is the larger SAG mill. By buying a larger mill now, Gen Mining has simplified the plant and built in the full 10.1 million tonnes per year of capacity from the outset, rather than paying approximately C$12 million to expand later. In the feasibility study, the throughput in years 1-3 was expected to be 8.9 million tonnes per year. This substitution has been confirmed by metallurgical testing.

“Our focus is on making decisions today that improve both how we build Marathon and how it performs for years to come,” said Clinton Swemmer, Vice President, Projects, of Generation Mining. “The larger SAG mill is a good example: it simplifies the plant, gives us full capacity from start-up and avoids future expansion costs. Together with our progress on engineering and earthworks at site, decisions like this are focusing the project team on a clear project schedule.”

Gen Mining also recognizes Vashee Mahalingasivam, Metso’s Regional Sales Manager – Central Canada, for bringing Metso’s equipment and service teams together around Marathon’s needs.

“Vashee has played a central role in bringing the right people together and developing practical options aligned with Marathon’s priorities,” added Mr. Swemmer.

“We are proud to partner with Generation Mining and privileged to have been selected as a technology and service provider. With our strong Canadian footprint and experienced local team, we are committed to supporting Generation’s success throughout the project and well into their operations,” said Giuseppe Campanelli, President for Metso North and Central America.

Long-Term Service Agreement

Gen Mining and Metso are also discussing a long-term service agreement under Metso’s Life Cycle Services (“LCS”) program. It would start with the crushing and grinding circuits and could extend to other plant equipment, covering spare and wear parts, maintenance support and supply arrangements.

This agreement increases the likelihood of future uninterrupted mill operation, since Metso staff will be on site for maintenance and repairs and comes with a process guarantee. Metso will also stock replacement parts on site on a contingency basis, saving a considerable amount of upfront costs. Any LCS agreement remains subject to final terms.

Progress at Site

  • Site Preparation: More than 30 hectares have been cleared by Superior Resources, and access road culverts have been upgraded for heavy equipment deliveries. Clearing will continue throughout the winter and is expected to stay well ahead of needs as construction proceeds.
  • Earthworks: Gen Mining has contracted JDS Energy and Mining Inc. to oversee the earthworks program, which will be carried out by mining contractor L. Fournier et Fils Inc. which has mobilized and is starting work on the construction water containment structures which will continue through the winter months. Water management has been contracted to Vault Pipelines Ltd.
  • Construction Camp: Now open, with food services provided through the B & M Venture Services Limited Partnership, a limited partnership among Biigtigong Nishnaabeg and the Morris Group, and approximately 100 people are now on site. The camp now consists of 280 beds and will ramp up to 800 beds as construction proceeds.
  • Permits: Construction permits are in hand, and all work follows permit requirements.
  • Long—Lead Time Equipment and Contracts: All long-lead time items have been ordered including the Engineering, Procurement, Construction Management Contract with Ausenco, CAT mining fleet, and transformers, in addition to the items previously announced including the grinding mills package, high voltage substation package, thickener package, primary crusher package, hydrocyclones, and pre-engineered process plant building. Deliveries of all items are currently expected in the required timeline.

Qualified Person

The scientific and technical content of this news release has been reviewed and approved by Clinton Swemmer, P.Eng., VP Projects of the Company, and a Qualified Person as defined under National Instrument 43-101 – Standards of Disclosure for Mineral Project.

About Generation Mining

Generation Mining Limited (TSX: GENM | OTCQB: GENMF) is a Canadian critical minerals development company focused on building the Marathon Copper-Palladium Project in Northwestern Ontario. The Company has commenced construction of the Marathon Project, one of Canada's largest undeveloped copper-palladium deposits and a future domestic source of copper, palladium, platinum, gold and silver.

The Marathon Project is expected to be a long-life, low-cost mining operation producing critical minerals essential to electrification, clean energy technologies and emissions reduction. Generation Mining is committed to responsible resource development through strong Indigenous partnerships, environmental stewardship and sustainable mining practices that create long-term benefits for local communities, Ontario and Canada.

For more information, please visit www.genmining.com.

Forward-Looking Information

This news release contains certain forward-looking information and forward-looking statements, as defined in applicable securities laws (collectively referred to herein as “forward-looking statements”). Forward-looking statements reflect current expectations or beliefs regarding future events or the Company’s future performance. All statements other than statements of historical fact are forward-looking statements. Often, but not always, forward-looking statements can be identified by the use of words such as “plans”, “expects”, “is expected”, “budget”, “scheduled”, “estimates”, “continues”, “forecasts”, “projects”, “predicts”, “intends”, “anticipates”, “targets” or “believes”, or variations of, or the negatives of, such words and phrases or state that certain actions, events or results “may”, “could”, “would”, “should”, “might” or “will” be taken, occur or be achieved, including statements relating to the Project remaining on track; the potential LCS agreement with Metso and its scope, terms, benefits and costs, including any process guarantee, on-site parts inventory and reduction in upfront costs; ongoing discussions with Metso regarding flotation equipment and pumps; the expected processing capacity of the Project from start-up and the expansion costs expected to be avoided by the larger SAG mill; the progress of engineering, procurement, contracting and site preparation, including earthworks, water management, site clearing and the expansion of the construction camp; procurement costs relative to the most recent feasibility study and construction budget; the expected timing of equipment deliveries; the forecast cost at completion and the sufficiency of the contingency portion of the construction budget; and the advancement of construction at the Project.

Forward-looking statements are based on a number of assumptions and are subject to known and unknown risks, uncertainties and other factors that may cause actual results to differ materially from those expressed or implied. Such factors include, among others: the risk that suppliers and contractors do not perform in accordance with their commitments, that costs increase materially beyond current estimates or that the larger SAG mill does not perform consistently with metallurgical testing; risks associated with the construction of the Project; the estimates and assumptions underlying the most recent feasibility study and construction budget; inflation and cost escalation, including fuel costs; the ability to reach definitive terms with Metso on any LCS agreement or on the supply of flotation equipment and pumps; equipment delivery, installation and performance; winter weather and site conditions; the availability of labour and accommodation; the ability to maintain agreements and relationships with Indigenous and community partners; operational, technical, environmental and permitting risks; and general economic, market and political conditions, as well as those risk factors set out in the Company’s annual information form for the year ended December 31, 2025, and in the continuous disclosure documents filed by the Company on SEDAR+ at www.sedarplus.ca.

Although the Company believes the expectations reflected in such forward-looking statements are reasonable, undue reliance should not be placed on them, as the Company can give no assurance that they will prove to be correct. Forward-looking statements are made as of the date of this news release, and the Company undertakes no obligation to update or revise any forward-looking statement, whether as a result of new information, future events or otherwise, except as required by applicable law.

View source version on businesswire.com: https://www.businesswire.com/news/home/20261124533307/en/